 Work Packages
Solution Student's question:
If it is the case that work packages can be broken into activities, tasks and sub-tasks, won't the tasks and sub-tasks be the lowest level (as long as the 80-hour rule or some rule is followed), or is it that the WBS does not recognize anything below the work package?

PMP Expert's Answer:
PMBOK: defines a work package as "a deliverable" at the lowest level of the WBS. Developed during the scope definition process, the work package can be further decomposed into activities (vs deliverables at the WBS work package level) during the activity definition process. This process of further decomposition produces the activity list which is an extension of the WBS.


Article Details
Article ID: 12
Created On: 03 Apr 2005 07:17 AM

 This answer was helpful  This answer was not helpful

 Back
 Search
Do not hesitate to use the search button to find articles and tutorials.

Simply enter your keyword, select the area where you want to search and press search.
 
 
 
 
 
 
If you have submitted a ticket to the support, you may login below to review its status.

Please note the support ticket password was sent to you when you submitted your first ticket.

When you are logged in, click on View Tickets from the Bottom bar.
 Login [Lost Password] 
Email:
Password:
Remember Me:
 
 Article Options
Home | Submit a Ticket | Knowledgebase | Troubleshooter | Downloads
 

Help Desk Software By Kayako eSupport v3.20.02