 Cost Reserve v. Management Reserve
Solution Student's Question:
Could you explain the difference between a cost reserve and a management reserve?
Are management reserves included with the project plan or added to it later or kept separate?

PMP Expert's Answer:
Contingency/cost reserve: A separately planned quantity allowing for future situations, included in the baseline and managed by the PMP. Known unknowns such as "we know we will have rework to do" just not sure how much. Management reserve: A separately planned quantity for future situations impossible to predict, unknown unknown. Not included in the original baseline budget and therefore requires a change in the baseline.


Article Details
Article ID: 10
Created On: 03 Apr 2005 07:15 AM

 This answer was helpful  This answer was not helpful

 Back
 Search
Do not hesitate to use the search button to find articles and tutorials.

Simply enter your keyword, select the area where you want to search and press search.
 
 
 
 
 
 
If you have submitted a ticket to the support, you may login below to review its status.

Please note the support ticket password was sent to you when you submitted your first ticket.

When you are logged in, click on View Tickets from the Bottom bar.
 Login [Lost Password] 
Email:
Password:
Remember Me:
 
 Article Options
Home | Submit a Ticket | Knowledgebase | Troubleshooter | Downloads
 

Help Desk Software By Kayako eSupport v3.20.02